Quantcast
Channel: SCN: Message List
Viewing all articles
Browse latest Browse all 9193

batch job for MRP and Planning filer entry

$
0
0

Dear Experts,

 

I have question regarding MRP batch run and sequence for running ...

 

I understand for MRP Batch run we need to follow below setting but I have some clarification needed

 

 

Scenario is like this

 

1) Planning plant  like say  P1001

 

I need to run MRP batch job every 12 midnight

 

I understand below  are the following setting

 

1) create variant for planning file entry for plant P1001  - MDAB and run batch job at 11 PM

 

2) create variant for MRP run MDBT and set batch job to run after planning file batch job completed

   now my question in this  step we need to set NETCH or NETPL or NEUPL what is the best practice

 

3) Do I need scope of planning if there is only one plant for MRP run ??

 

4)Do I need parallel processing if my plant is only one ?

 

5) I understand 

 

 

NEUPL: System plans all the materials that are contained in the planning file

 

can I set this indicator for monthly batch job ???

 

 

NETCH: In net change planning only those materials are planned for which the net change planning indicator in the planning file has been set as a planning file entry. The system usually sets the indicator automatically as soon as a change is made to the material that is relevant to MRP.

 

 

can we ignore this indicator while set up batch job ???

 

NETPL: The system only plans materials that have undergone a change that is relevant to the planning run within the period which you defined as the planning horizon. The system sets the net change planning horizon indicator automatically for these materials .

 

can I set this indicator to set daily batch job ???

 

 

I know this topic has  discussed many times in this forum , if u help to answer for this question or give me a right links will more thankful

 

Regards

Raj


Viewing all articles
Browse latest Browse all 9193

Trending Articles