Hi,
1. Create BOM for the FG materials X, Y and Z
The total receipt quantity is 12 (2+3+7) EA for 1 EA of A. So you have to calculate the material consumption like that.
So, for 2 EA of X, material A to be consumed is 2/12 = 0.17
For 3 EA of Y, material A to be consumed is 3/12 = 0.25
For 7 EA of Y, material A to be consumed is 7/12 = 0.58
Hence the total consumption of material A is 0.17 + 0.25 + 0.58 = 1 EA
- Header: X (2 Qty)
Item: A , qty : 0.16 EA If you are maintaining BOM for 1 EA of X, qty of material A required is = 0.16/2 = 0.083 EA
- Header: Y (3 Qty)
Item: A, qty: 0.25 EA If you are maintaining BOM for 1 qty of Y, the qty of material A required is 0.25/3 = 0.083
- Header: Z (7 Qty)
Item: A, Qty: 0.58 EA
If you are maintaining BOM for 1 EA of Z, qty of material A required is 0.58/7 = 0.083
2. Create subcontract PO for material X and Y and Z for quantity 2 , and 7 respectively.
3. Issue the material A (1 quantity) to the subcontract vendor against the subcontract PO using 541 movement with MB1B transaction.
4. Receive the material X, Y and Z against the subcontract PO.
5. Check the consumption of material A.
Regards,
AKPT