Hi Ashely,
To link the orders to your Network Internal Activities.
You need to maintain the Order / Network relationship (Control parameters for subnetworks - OPTP) and Settlement Profile needs to be maintained for networks (Settlement Optional).
After doing these two settings, you can assign the Network and Internal activity to the maintenance order.
Regards